Q: How long does the process take?
A: For a Pool only (no spa) it takes 4 to 6 weeks, Pool/Spa combo takes 6 to 8 weeks.

Q: Do I have to put down a deposit?
A: No, the first payment is due the day we show up to start excavation.

Q: How do we pay for the pool?
A: We have a four payment schedule: 35% at excavation, 35% at Gunite, 25% at deck, 5% at Plaster.

Q: Do I need to be home for all phases?
A: No, most of the time we do not need access to your house. When the electrical is scheduled, we will need access to your electrical panel and may need to access the attic or the garage, but we will let you know a day in advance.

Q: Do I have to do anything during the construction process?
A: Yes, there are a couple of things we will need for you to do. First is after we do the Gunite we will ask you to water down the shell of the pool twice a day for 7 days. We will explain how to do that. Second is making your choices for tile and coping or rock. We will bring the tile samples to you, but for coping or rock choice, we may ask you to meet us at the rock yard to pick it out.

Q: Will there be someone in my yard every day once you start?
A: No, there may be days that no one is working on your pool. There are inspections that need to be done and we cannot touch the site once we prepare for the inspections. Weather can also delay our work and certain phases may be delayed a day or two for scheduling purposes. We make every attempt to complete your pool within the above timelines.

Q: Do you provide financing?
A: Yes, we have a company that we work with for your financing needs.